Photo report | July, 2024 | Felicity residential complex
30.07.2024
Our builders have completed the installation of vertical structures on the 1st floor in sections 1.3 and 1.4
.
Also, the floor of the 1st floor of sections 1.3 and 1.4 is 100% ready. The vertical structures of the 1st floor of the same sections have also been successfully completed.
This month, we started to install the formwork for the floor slab of the 2nd floor of sections 1.3 and 1.4. At the same time, we started waterproofing the parking lot.
There will be more and higher, so stay tuned for changes in the construction of Felicity.